August 17, 2022
The COVID-19-induced supply chain meltdown made it difficult to complete our facility: stainless steel, microcontrollers, and other critical components were extremely delayed if not almost impossible to find. Our founder was quoted as saying: “I would 10/10 not recommend building a high-energy radiation facility in the midst of an epochal supply chain implosion.”
But our team worked very hard, took on more of the integration work than expected, and employed novel strategies to hold to schedule as much as possible.
Finally, on August 17, we completed a long list of qualification and validation tests and were finally able to process our first several pallets (wrapped, as always, in NextBeam Orange).
Onward! 🙂
Additional Articles We Think You Might Like
Have a question? Speak with a sterilization expert today, at your own convenience.
When do I need to notify authorities or get approvals and how long does this take? A gratuitous disclaimer up front: we at NextBeam are not regulatory experts. However, we are periodically asked by...
ISO 11137-1:2025 has officially been published, marking the first update since 2006. The changes are far-reaching and impactful, reflecting the evolving needs of the medical device industry—while also...
North Sioux City, SD – – NextBeam, a leading provider of Electron Beam irradiation services, is pleased to announce the launch of the NextBeam Research Fellowship, a new initiative designed to...